“Construction projects are continuing to make headway across the district, improving the safety and mobility of our state’s infrastructure,” Simmons said. “Please slow down and stay alert for both construction and maintenance crews working to see these projects through.”
“We appreciate the public allowing our crews the time and space to make these interstates safer and smoother,” Simmons said. “During remaining work hours, please continue to stay vigilant for our crews and slow down when approaching active work zones so we can finish up this critical improvement project as quickly and efficiently as possible.”
Remaining work will continue during overnight hours to limit the impact to traffic. The $14 million project was awarded to Dickerson & Bowen, Inc. of Jackson, Mississippi. The project remains on track to wrap up this fall.
Crews have completed pressure grouting concrete in failed areas, turn lane widening at Star Road and Eagle Post Road, ditch repair south of Stay Road, and punchout repairs in concrete pavement. Mainline paving operations are also complete. Guardrail is being installed across the project limits with shoulder gravel placement to follow.
Your local Wirtgen America dealer |
---|
Kirby Smith Machinery |
Power Equipment Co |
The $11.4 million project was awarded to APAC-MS, Inc. of Jackson. Lane closures will take place overnight to limit traffic impact. Remaining work is expected to wrap up by the end of this year.
Work in progress includes clearing and grubbing, milling southbound SR 19 lanes, building county roads onto the new alignment, removing old box culverts and bridges, constructing new ones, and hauling borrow and excess excavation.
Phase III will place traffic in the four-lane configuration, apply the final lift of asphalt, and provide permanent striping. The $36 million contract was awarded to W.G. Yates and Sons Construction of Philadelphia, Mississippi. Remaining work is expected to wrap up later this year.
Temporary construction signs are in place to alert the public of the overnight lane closures. Bearing pad replacements, epoxy repairs, and cleaning bridge caps are complete, and crews recently finished the hybrid polymer concrete overlay along with thermoplastic striping and raised pavement marker placement.
Remaining work includes the placement of fencing along the slope, paving, and miscellaneous cleanup. The $2.4 million contract was awarded to Key, LLC of Madison, Mississippi, and will be completed by the fall.
Construction signs are in place, and the pressure grouting and failed area repairs are complete. Mainline paving, clearing, fence repair, and joint sealing work remains underway. The $28.2 million contract was awarded to APAC-MS. The anticipated completion date is summer 2025.
Crews have completed the ramp widening. Milling, paving, and guardrail repairs are underway. The $9.9 million project was awarded to Superior Asphalt of Byram, Mississippi. Work is expected to wrap up this fall.
Work underway consists of clearing, grubbing, and fence removal. The closure of the exit ramp will remain in place until approximately October 11 to allow crews to safely perform the work. Signs are in place to alert southbound drivers of the closure and detour, which will direct traffic to exit at Sowell Road and take I-55 north back to Nissan Parkway.
The $2 million project was awarded to Key, LLC. The remainder of the project is expected to wrap up next summer.